The Natural Landscape – Beginning of the Journey (Now – March 2025)
At the heart of Namibia, this untouched landscape symbolizes the foundation of Oshili Power’s commitment to sustainable development. As we prepare for the build-up phase, this land will soon transform into a hub of clean energy, driving progress for both the environment and local communities. Over the next few months, we are securing key agreements and finalizing the necessary groundwork to launch construction in March 2025.
The Start of Construction – Laying the Foundations (March 2025)
With construction officially underway, we are turning ambition into action. This phase marks the beginning of physical progress as we break ground to lay the infrastructure for 600MW of solar power. As construction unfolds, we are committed to transparency and open dialogue with local communities, ensuring that every step benefits the surrounding areas through job creation and opportunities for local businesses..
~Actual timelines will be confirmed at financial close
First 120MW Connected to the Grid – Delivering Energy, Building Trust (~8 Months After Construction Begins)
The first 120MW of solar energy is connected to the grid, marking a critical milestone in our journey. This phase represents Oshili Power’s first delivery of clean, renewable energy, a tangible result of our efforts. As investors and stakeholders, you’ll see the early success of this project as a testament to our commitment to energizing Namibia and building trust with our community partners.
~Actual timelines will be confirmed at financial close
Phase 2 Construction Complete – 240MW Online, Growing Momentum (~10 Months After Construction Begins)
As the second phase of construction wraps up, an additional 120MW is connected to the grid, bringing our total to 240MW. With each milestone, we are increasing our positive impact on Namibia’s energy independence while engaging local communities through education programs and workshops on renewable energy. This continued progress highlights the project’s momentum and reliability, reassuring investors of the tangible returns ahead.
~Actual timelines will be confirmed at financial close
Phase 3 Construction Complete – 360MW Energized (~12 Months After Construction Begins)
With 360MW now online, Oshili Power’s solar farm reaches a significant turning point, powering homes and industries across Namibia. The project’s scale becomes ever more evident, and our community engagement deepens as we continue to create job opportunities and support local growth. This milestone demonstrates to our investors and stakeholders that Oshili Power is well on its way to achieving its full potential.
~Actual timelines will be confirmed at financial close
Phase 4 Construction Complete – 480MW Operational (~14 Months After Construction Begins)
At 480MW, the project stands close to completion, with Namibia now reaping the rewards of a more sustainable energy supply. Oshili Power continues to work hand-in-hand with local leaders and stakeholders to ensure that this growth benefits everyone, from schools and community organizations to businesses. As we approach the final phase, we remain steadfast in delivering on our commitments, ensuring both environmental and economic value.
~Actual timelines will be confirmed at financial close
Phase 5 Construction Complete – Full 600MW Commissioned (~16 Months After Construction Begins)
The final phase marks the completion of Oshili Power’s ambitious 600MW solar farm. Now fully operational, this landmark project represents the future of clean energy in Namibia. It’s a moment of pride for our investors, stakeholders, and community partners as we celebrate not only the delivery of energy but the long-term, sustainable impact on local economies and the environment. Together, we’ve built more than just a solar farm—we’ve built a brighter future for all.
~Actual timelines will be confirmed at financial close